    1 Todo
     1[[PageOutline]]
     2[wiki:ENWikiStart Home] > [wiki:ENOptimProcess OptimProcess] > [wiki:FROptimProcessImprimeurs Printer] > [wiki:ENOptimProcessMachinesPliage Folding]
     3
     4
     5 = Gate and window folds =
     6
     7To add a new machine you go to 4 menus:
     8
     9 * characteristics
     10 * quantities
     11 * grammage
     12 * delivery
     13
     14 == Characteristics ==
     15
     16Vous accédez aux caractéristiques techniques de la machine qui se décomposent en 6 rubriques.
     17
     18 === Informations générales ===
     19
     20Eou go to the technical characteristics of the machine which breaks down into 6 categories.
     21
     22 * her name
     23 * is it active in the calculation?
     24 * it is contrary to internal or do you use a subcontractor?
     25
     26 === Authorized trim size ===
     27
     28Define the authorized trim size by choosing in the drop-down menu.
     29
     30 === Open size ===
     31
     32It corresponds in going size with 2 fields to fill:
     33
     34 * height ( minimum et maximum) which corresponds to the width of the buckle
     35
     36 * lenght (minimum et maximum) which corresponds to the depth of the buckle.
     37
     38These 2 sizes are set in millimeters.
     39
     40An option is available to determine if the size adjustment in included in the rate folding.
     41
     42 === Max. paper weight assuming pre-scoring ===
     43
     44Set a maximum weight for 2 window folds and 3 gate folds.
     45
     46There is the possibility to choose if the sizing before folding is included in cost. If so, this means that guillotine costs will not be counted.
     47
     48This table sets the maximum weight under understood that the fold will be possible soon if the product will be asked for a lower weight to it.
     49
     50 === Fixed costs ===
     51
     52Fixed costs are the costs of makeready, which are determined:
     53
     54 * a makeready cost for 2 window folds
     55 * a makeready cost for 3 gate folds
     56 * possibly a free from a number of copies
     57
     58 === Proportional costs ===
     59
     60The proportional costs correspond to the cost of 1000 copies:
     61
     62 * a cost of 1000 copies for 2 folds
     63 * a cost of 1000 copies for 3 folds
     64
     65 == Quantities ==
     66
     67This screen allows you to make a variation of a standard price per 1000 according to quantities( per steps).
     68
     69Each rule is applicable individually and the system takes into account the most advantageous.
     70
     71WARNING: If you set :
     72
     73< 2000 runs then variations -10%
     74
     75< 3000 runs then variations -5%
     76
     77n this case, for a quantity of 1000, the system will take a variation - 10%.
     78
     79  The rules are put into competition in their field of validity. If both rules are checked, the most advantageous being chosen.
     80
     81 == Grammage ==
     82
     83This screen lets you set increases depending on steps of weights to simulate the change in pace of machines.
     84
     85 == Delivery ==
     86
     87This pop up allows you to pricing, if the machine is externally (from a subcontractor), the cost of transport return from the printer to the subcontractor.
     88
     89There are 3 ways to price:
     90
     91 * with a fixed cost
     92 * with a proportional cost per kg
     93 * with a minimum outright cost.
     94